Step 6... The Building Continues... Nearly There

Sides now on, the building is nearly there. 

    

 

Step 5... Construction Begins

With the stell frames being put into place you can really see things coming into the shape. 

  

Step 4... Steel Delivery & Fabrication

Feet and joining plates had to be welded before the stell frame could be put into place.

   

Step 3... Brake Roller Casette Installed & Concrete Poured

 

   

     

       

   

 

Step 2... Groundworks & Foundations

Groundworks continue and foundations laid at Redvers Motorhome Repairs preparing for Roller Brake Tester Cassette to be installed.

 

     

 

       

 

 

Step 1... Groundworks

Groundworks started on site on 6/7 th November in preparation for the next step. 

                                     

 